Code of conduct for lifting steel plates in workshops

  In order to facilitate the lifting of steel plates, most of the steel workshop is equipped with a crane, which is similar to a gantry crane, but the operation of the car is more flexible, and it can be translated before and after in the whole workshop under the control of remote control, through the track on both sides, and the coverage of its operation can reach 90%.

  Lifting pliers Lifting steel plate workshop is equipped with a crane, through the crane to connect the lifting pliers, you can move the steel plate in all directions.

  Driving workers must pay attention to the process of steel plate lifting:

  First of all, move the truck to a line with the center line of the steel plate, then translate the crane, and move the crane horizontally to the top of the steel plate.

  Then lower the lifting pliers, and fix the steel plate through the lifting pliers. After fixing, lift the sling until the sling is in a half tension state, and adjust the left and right positions to ensure that the hook is perpendicular to the center of gravity point of the steel plate.

  Finally, slowly lift, lifting height can not be too high, translation on the way must pay attention to observe the people and things around, to avoid pedestrians is the most basic use of norms of behavior, while in the translation process to remind the workshop pedestrians to pay attention to lifting objects. Then is to avoid obstacles, as long as there is a collision may cause the lifting pliers to fall off, so the whole lifting process must be done, careful slow, more observation, more reminders.

  This is the code of conduct of the workshop crane lifting steel plate.